Owner: Parkway Utility District
Engineer: Quiddity
Notice to Proceed: 07/21/2021
Substantially Completed: 6/29/2022
Contract Amount: $1,174,493.81
Description of Work: Demolition of existing lift station wet well, dry well, pumps, piping, concrete, chain link fence, asphalt pavement, generator, control panel, and service rack. Construct a twelve foot (12′) diameter cast-in-place concrete wet well; three (3) submersible pumps with guide rails, piping, fittings, valves, pipe supports, and pump lifting chains; concrete pavement; diesel generator with sub-base fuel tank and slab; service rack and control panel with slab; eight foot (8′) cedar fence with sliding gate and pedestrian gate; site grading; bypass pumping system setup and 24/7 monitoring; water service line, backflow preventer and hose bibb; wet well vent, odor control valves, and bollards; junction manhole and influent sewer lines; all electrical facilities including junction boxes, cellular autodialer, floats, transducer, conduits and conductors; and all else necessary for a complete and functioning lift station.