Owner: B-E Development, Inc. obo Lumberton MUD
Engineer: Elevation Land Solutions
NTP: 11/28/2022
Expected Completion: 09/25/2023
Contract Amount: $1,079,839.92
Description: Construction of a fully functional lift station which includes construction of a 36’ deep, 10’ x 10’ Precast Concrete Wet Well w/ cast in place bottom & top slabs, 2 submersible pumps with discharge piping & valves, access hatches, protective coatings, control panel, automatic transfer switch, float switches electrical installation & startup, underground sanitary sewer pipe & manholes, site work concrete pavement, emergency natural gas generator, fencing & gates.