Call Us At : (713) 904-4811 support@zeus-con.com

Owner: Harris County Municipal Utility District No. 213A

Engineer: Quiddity

Notice To Proceed: TBD

Expected Completion Date: TBD

Contract Amount: $1,763,000.00

NTP : 09/30/2022

Anticipated Substantial Completion: 07/1/2023

Description of Work:

Construction of a fourteen-foot (14’) diameter concrete wet well and 8’x20’ concrete discharge trough, well point system and dewatering as necessary; two (2) mixed flow pumps with accessories; piping; valves; fittings and supports; protective coatings; site work; concrete panel fencing with swing gate; concrete pavement; on-site storm sewer piping including well point system and dewatering as necessary; storm junction box and manholes; natural gas engine driven generator; automatic transfer switch and load bank testing; pump station control panel; electrical service; disconnect switches; conduit; wire; and all else necessary for a fully functioning pump station.

Skip to content